The Galsi Pipeline will provide a new source of natural gas for Italy with the goal of guaranteeing a secure energy resource and supplying Sardinia with natural gas.
The pipeline will begin 21 km east of Annaba in Algeria, at the location of a proposed compressor station where gas will be brought to the correct pressure for injection into the subsea pipeline. The pipeline will then cross 280 km from Algeria to Italy, of which approximately 100 km will be laid at a depth of 2,800 m, before reaching Sardinia at Porto Botte.
At Porto Botte the gas pressure will be reduced, and a 48 inch diameter pipeline will traverse Sardinia from south to north for approximately 300 km to reach Olbia.
At Olbia the gas will be compressed again in the second compressor station for injection into the 32 inch subsea pipeline, which will be constructed at a maximum depth of 850 m. After a marine crossing of 275 km the Galsi Pipeline will terminate at Piombino, Tuscany, where it will connect to the Italian gas distribution network.
Article continues below…
Not only is the 8 Bcm/a capacity pipeline to be constructed in very deep waters, but it will require a heavy wall thickness of pipe to withstand collapse. This in turn requires a construction contractor with unique capabilities.
Extreme depths
JP Kenny completed front-end engineering and design for the pipeline in 2009.
The onshore pipeline is to be made of carbon steel with a minimum thickness of 16.1 mm, while the offshore pipeline will have a thickness of between 18 and 37 mm.
Galsi Project Manager Arcangelo Perrone says “The extreme water depths in which the pipeline is to be installed and the large diameter of the pipe means that the pipe wall needs to be very thick to be able to withstand collapse due to external pressure.”
In order to contain the wall thickness and weight, X70 pipe has been selected and the fabrication tolerances have been reduced compared to the standard.
“These sizes and thicknesses are the limit of production capacity of many pipe mills, and presently only a couple have confirmed the capacity,” says Mr Perrone. “Other mills would require expansions, upgrades or retooling to provide pipe for the project.”
Selecting a pipeline route
Fugro was contracted to undertake detailed marine surveys to identify the route of the pipeline. The complex morphology of the seabed, characterised by steep continental margin slopes, meant that selecting a route for the pipeline was a difficult task.
Eight offshore and near-shore vessels were employed to complete the marine survey, which took ten months to complete.
Selecting a suitable route for the onshore Sardinia section of pipeline was challenging due to a number of environmental restrictions, including protected archaeological sites, which ran through the proposed route.
Contractor D’Appolonia completed many environmental studies to avoid the most sensitive areas.
Challenges for construction
Once ready for construction, pipe will be welded on a moving platform and lowered gradually onto the sea floor via a laybarge. Pipe installation methods will include both ‘S-lay’ and ‘J-lay’ methods.
The ‘S-lay’ method can be used in both shallow water and deepwater pipelines up to a depth of 3,000 m. The pipe is welded horizontally and lowered into the sea supported by a curved pontoon structure known as a stinger, which forms an elongated ‘S’.
The ‘J-lay’ system is used to lay pipelines at depths between 400 and 3,500 m. The pipe is welded in a vertical position and lowered onto the sea floor without the use of a support structure, thus forming a ‘J’ shape.
Mr Perrone says that the extreme water depth and the large diameter of pipe limit the number of contractors that have the technology and capability to lay the pipeline.
“The project will induce most contractors to upgrade their pipelay vessel,” he says.
Other operations in deep water for both offshore sections of the pipeline, including shore crossings, span corrections by trenching and rock dumping, will also require the review and possible upgrade of equipment.
“Similarly, pipeline repair and retrieval equipment will have to be upgraded,” says Mr Perrone.
A dedicated team
In addition to personnel from JP Kenny, Fugro and D’Appolonia, Galsi has a team of 20 consultants that is dedicated to the project.
Construction of the pipeline is expected to commence in 2011 and be complete in 2014.
Mr Perrone says “The Galsi Pipeline has been recognised as a strategic and very important project not only by both countries, Italy and Algeria, but also from the European Union because it will provide a new direct, secure and economically competitive line for the supply of natural gas. The team of experts is engaged to lead this project to realisation and to achieve a great feat of technology and engineering.”